Modeling stochastic project time-cost trade-offs with time-dependent activity durations.
Abstract
In real-life projects, both the trade-off between the project cost and the project completion time, and the uncertainty of the environment are considerable aspects for decision-makers. Moreover, in some projects, activity durations show their complexity with time-dependence as well as randomness. In this paper, a stochastic time-dependent time–cost trade-off problem is introduced. To meet different management requirements, three stochastic time–cost trade-off models are built. The proposed models are dealt with an intelligent algorithm combining stochastic simulations and genetic algorithm, where stochastic simulation technique is employed to estimate random functions and genetic algorithm is designed to search optimal schedules under different decision-making criteria. Finally, some numerical experiments are given to illustrate the algorithm effectiveness.
Year
DOI
Venue
2012
10.1016/j.amc.2012.03.035
Applied Mathematics and Computation
Keywords
Field
DocType
Time-dependent time–cost trade-off,Stochastic programming,Stochastic simulation,Genetic algorithm
Stochastic simulation,Stochastic optimization,Mathematical optimization,Computer science,Schedule,Trade offs,Stochastic programming,Genetic algorithm,Randomness
Journal
Volume
Issue
ISSN
218
18
0096-3003
Citations 
PageRank 
References 
2
0.38
8
Authors
3
Name
Order
Citations
PageRank
Hua Ke110413.34
Weimin Ma242726.76
Xiaowei Chen320.38