Due Date-Based Metrics for Activity Importance in Stochastic Activity Networks
Abstract
A metric pair for assessing the importance of activities in stochastic activity networks based on completing a project on time (or reaching other project milestones) is presented. The metric pair is recommended as a supplement to other metrics of activity importance that have been suggested for use with Monte Carlo simulation. The differences in behavior of the various metrics are analyzed to help understand the additional types of insights that would be available by including the new metrics in simulation-based analyses.
Year
DOI
Venue
2001
10.1023/A:1010993713274
Annals OR
Keywords
Field
DocType
PERT,project management,stochastic activity networks,activity criticality,conditional estimators,Monte Carlo simulation
Mathematical optimization,Monte Carlo method,Industrial engineering,Computer science,Simulation,Milestone (project management),Project management
Journal
Volume
Issue
ISSN
102
1-4
1572-9338
Citations 
PageRank 
References 
3
0.56
3
Authors
1
Name
Order
Citations
PageRank
R. Alan Bowman1213.51