Scheduling a multi-chip package assembly line with reentrant processes and unrelated parallel machines
Abstract
A multi-chip package (MCP) consists of several chip modules in a single package. We consider a scheduling problem for assembling MCPs. In order to assemble an MCP, a lot should repeat assembly process stages such as die attach and wire bonding as many as the number of chips to be assembled. The two key process stages have many parallel machines of various types. A machine processes different types of MCP lots with significant setup times. We therefore should limit the number of setups significantly while not sacrificing the on-time delivery performance much. We propose scheduling strategies of appropriately allocating the machine capacity to products and lots depending on the production progress of products and lots. We report experimental performances of the proposed methods.
Year
DOI
Venue
2008
10.1109/WSC.2008.4736332
Winter Simulation Conference
Keywords
Field
DocType
chip module,die attach,assembly process,scheduling,reentrant processes,single package,machine capacity,multichip modules,assembling,machine processes,multichip package assembly line,assembly process stage,different type,mcp lot,unrelated parallel machine,multi-chip package assembly line,scheduling strategy,scheduling problem,multi-chip package,wire bonding,parallel machine,parallel machines,reentrant process,key process stage,simulation,chip,mean squared error
Delivery Performance,Wire bonding,Job shop scheduling,Scheduling (computing),Computer science,Mean squared error,Chip,Embedded system,Reentrancy
Conference
ISBN
Citations 
PageRank 
978-1-4244-2708-6
1
0.37
References 
Authors
7
2
Name
Order
Citations
PageRank
Sang-jin Lee136040.96
Tae-Eog Lee228530.02