Resource-constrained project scheduling with activity splitting and setup times.
Abstract
•A meta-heuristic solution approach using extended networks is presented.•Four types of setup times using activity segments are used.•A logical boolean optimizer is used to solve conflicts.•The impact of network and resource parameters on the makespan reduction is investigated.
Year
DOI
Venue
2019
10.1016/j.cor.2019.05.004
Computers & Operations Research
Keywords
Field
DocType
Project scheduling,RCPSP,Activity preemption,Setup times
Schedule (project management),Mathematical optimization,Preemption,Job shop scheduling,Boolean satisfiability problem,Schedule,Project network,Solver,Project networks,Mathematics